Time / Date: 7/24/2023 9:40:03
|
JSP ID: 1297
|
Scope of Work: Reset tripped breaker feeding receptacles in 1275
|
|
Work Order:
|
Building: 50B
|
Person in Charge: Andrew Southward
|
Lead / Supervisor: Cameron, Benjamin
|
Logged Email: amsouthward@lbl.gov
|
Division: Facilities
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Alma Duran
|
|
List Other Participants:
|
|
Affected Persons Notified: Yes
|
Switching: Hazardous Switching
|
Panel / Equipment ID: 38A10A5A
|
System Information Review: Panel Schedules, Arc Flash Labels
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition: Properly installed, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
Unplug equipment from receptacles, inspect for likely cause of tripped breaker, obtain permission from engineering to switch( over dutied panel) reset breaker and switch on. |
Control of Work Area
Minimum Approach Boundary: 42
|
Barricade Tape / Attendant:
|
Shock Risk Assessment
System Voltage: 120/208 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: No
|
Voltage Glove Class: Not Required
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 0.42 cal/cm2
|
Arc Flash Boundary: 10 inches
|
Working Distance: 18 inches
|
Arc Flash PPE Level: 1
|
Incident Energy Reduction Measures: Not Required
|
Capacitor Hazards
Capacitor Bus Voltage: Na
|
Capacitor total stored energy (joules): Na
|
Discharge wait time (minutes): Na
|
Emergency Response Plan
Nearest Landline Location: 1275
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: On hand
|
Fire Extinguisher Location: Outside 1275
|
Contact release method available and tested: Upstream breaker or switch, Voltage gloves
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
Lookalike equipment, Noisy environment, Over duty panel |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
None |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |