Time / Date: 9/26/2023 11:12:21
|
JSP ID: 1599
|
Scope of Work: ZVV at disc 16A 480vac
|
|
Work Order: 1234
|
Building: 75A
|
Person in Charge: CWoo
|
Lead / Supervisor: Other
|
Logged Email: konecliff@gmail.com
|
Division: Facilities
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Derek Mccabe
|
|
List Other Participants: Ari Harding - LBNL EHS
|
|
Affected Persons Notified: Yes
|
Switching: No Switching Required
|
Panel / Equipment ID: 16A
|
System Information Review: Arc Flash Labels,
|
|
Control of Hazardous Energy: Complex LOTO w/ RI
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
1. Join RI LOTO. 2. Open 16A panel=our elev control. 3. ZVV 16A Load side. 4. Do repairs. 5. Close 16A panel = our elev control. 6. Remove my lock from RI group lock. |
Control of Work Area
Minimum Approach Boundary: Greater the LAB or is 42” vs arc flash 26”
|
Barricade Tape / Attendant: Attendant
|
Shock Risk Assessment
System Voltage: 277/480 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 00
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 2.37 cal/cm2
|
Arc Flash Boundary: 26
|
Working Distance: 18 inches
|
Arc Flash PPE Level: 2
|
Incident Energy Reduction Measures: 00
|
Capacitor Hazards
Capacitor Bus Voltage: NA
|
Capacitor total stored energy (joules): NA
|
Discharge wait time (minutes): NA
|
Emergency Response Plan
Nearest Landline Location: B75 in hallway
|
Emergency Number to Call: 7911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: On wall right hand south
|
Fire Extinguisher Location: Outside west door and is charged
|
Contact release method available and tested: Upstream breaker or switch
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
Task Demands: Time pressure (in a hurry), High workload (memory requirements)
|
Work Environment: Distractions/interruptions
|
Individual Capabilities: Unfamiliar with, or first time performing task, New technique not used before
|
Human Nature: Stress (limits attention)
|
Error Precursor Mitigations:
Step by step procedure JSP Job Safety Plan |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
Practical test for QEW 2 level
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |