List basic sequence of steps from start to finish
Inform Control Room intention of applying the LOTO,
Secure the power suply,
Isolate the supply and return,
LOTO E120 [2] - 1,
Open flow switch cover,
ZVV,
Remove wiring,
Replace with new flow switch,
Rewire,
Place back flow switch cover,
Return water to the circuit,
Check for leaks,
Inform control Room intention of removing the LOTO,
Remove LOTO,
Test power supply