Time / Date: 10/25/2023 16:59:10
|
JSP ID: 1750
|
Scope of Work: Replace Rectifier Flow Switch - 8W598 Section D
|
|
Work Order: NA
|
Building: B88
|
Person in Charge: Ken Lambert
|
Lead / Supervisor: Other
|
Logged Email: mkireeffcovo@lbl.gov
|
Division: Other
|
QEW Level: QEW 1
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Not Required
|
|
Second Person Identified: NA
|
|
List Other Participants: MIchel Kireeff COvo
|
|
Affected Persons Notified: Yes
|
Switching: Non-Hazardous Switching
|
Panel / Equipment ID: Bending Magnet EE40
|
System Information Review: print 8W598
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
Inform Control Room intention of applying the LOTO, Secure the power suply, Isolate the supply and return, LOTO E120 [2] - 1, Open flow switch cover, ZVV, Remove wiring, Replace with new flow switch, Rewire, Place back flow switch cover, Return water to the circuit, Check for leaks, Inform control Room intention of removing the LOTO, Remove LOTO, Test power supply |
Control of Work Area
Minimum Approach Boundary: 42
|
Barricade Tape / Attendant: Attendant
|
Shock Risk Assessment
System Voltage: 120 Vac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 3 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: NA cal/cm2
|
Arc Flash Boundary: NA
|
Working Distance: No Arc Flash Hazard Present
|
Arc Flash PPE Level: Minimum PPE for Electrical Work
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage: NA
|
Capacitor total stored energy (joules): NA
|
Discharge wait time (minutes): NA
|
Emergency Response Plan
Nearest Landline Location: Switching Gear Room, next to the door
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: Front of the building
|
Fire Extinguisher Location: Switching Gear Room, next to the door
|
Contact release method available and tested: Voltage gloves
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
None |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |