QEW 1 / 2 / 3 Job Safety Plan

Electrical Safety
Back to Index
Time / Date: 12/15/2023 10:27:27
JSP ID: 1986
Scope of Work: Relocate a 3 phase 208 twist lock receptacle from outside the building to inside the building.

General Information

Work Order
359280
Building
77
Person in Charge
Anthony Pilz
Lead / Supervisor
Secheck, Stephen
Logged Email
apilz@lbl.gov
Division
Facilities

Work Planning

Modes of Work
☑ Mode 1 - LOTO & Zero Voltage Verification
QEW Level
QEW 2
Second Person Requirement
Standby Person
Second Person Identified
Shane Miller
Other Participants
Affected Persons Notified
Yes

System / Equipment

Switching
Non-Hazardous Switching
Panel / Equipment ID
86A28A
System Information Review
☑ Panel Schedules
Control of Hazardous Energy
Simple LOTO
Equipment Condition
☑ Properly installed
☑ Properly maintained
☑ All doors and covers closed and fully latched
☑ No signs of impending failure
☑ Not energizing equipment for the first time
☑ or after electrical repair

Sequence of Job Steps

List basic sequence of steps from start to finish
Don PPE LOTO and ZVV Take receptacle and box out of the shed Relocate to wall before the penetration. Release LOTO ReEnergize

Control of Work Area

Minimum Approach Boundary
71in
Barricade Tape / Attendant
Attendant

Shock Risk Assessment

System Voltage
120/208 V ac
Limited Approach Boundary
42 inches
Restricted Approach Boundary
12 inches
Will the hands enter the RAB
No
Voltage Glove Class
00
Will any other part of the body enter the RAB
No

Arc Flash Risk Assessment

Incident Energy
14.2 cal/cm2
Arc Flash Boundary
71 inches
Working Distance
No Arc Flash Hazard Present
Arc Flash PPE Level
Minimum PPE for Electrical Work
Incident Energy Reduction Measures
00

Capacitor Hazards

Capacitor Bus Voltage
Capacitor Total Stored Energy (Joules)
Discharge Wait Time (Minutes)

Emergency Response Plan

Nearest Landline Location
B77-242
Emergency Number to Call
x6999 / 911
Sufficient Cell Phone Signal
Yes
Clear Exit Path
Yes
AED Location
B77-239
Fire Extinguisher Location
B77-242
Contact Release Method Available and Tested

Environmental Conditions

Does the environment present additional hazards that should be addressed?
None

Error Precursors

Task Demands
Critical steps or irreversible acts
Work Environment
Distractions/interruptions
Individual Capabilities
Human Nature
Mind-set
Error Precursor Mitigations
Take our time and no rush

PPE Inspections

☑ Safety glasses (ANSI Z87)
☑ Arc-rated clothing (flash suit
☑ daily wear) including face shield
☑ balaclava
☑ hood.
☑ Hearing protection
☑ Rubber insulating gloves and leather protectors
☑ Non-melting footwear that fully covers the feet
☑ Removal of conductive articles
☑ Insulated tools
☑ Multimeter and other electrical test instruments

Notes / Other

Perform Job Briefing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan