Time / Date: 5/8/2024 13:48:20
|
JSP ID: 2550
|
|
Scope of Work: Close breaker for roll-up door
|
|
|
Work Order: W0381594
|
Building: 77A
|
|
Person in Charge: greg neidiger
|
Lead / Supervisor: Secheck, Stephen
|
|
Logged Email: greg.neidiger@gmail.com
|
Division: Facilities
|
|
QEW Level: QEW 2
|
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition
|
|
|
Second Person Requirement: Not Required
|
|
|
Second Person Identified: Steven Sechak
|
|
|
List Other Participants:
|
|
|
Affected Persons Notified: N/A
|
|
|
Switching: Hazardous Switching
|
Panel / Equipment ID: 72D-58
|
|
System Information Review: Panel Schedules, Arc Flash Labels
|
|
|
Control of Hazardous Energy: LOTO Not Required (Mode 2 or 3 only)
|
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
|
Sequence of Job Steps
|
List basic sequence of steps from start to finish.
1) Remove admin lock and have FATSE2 electrician remove his lock 2) Don PPE and switch |
Control of Work Area
|
Minimum Approach Boundary: 56
|
|
Barricade Tape / Attendant:
|
Shock Risk Assessment
|
System Voltage: No Shock Hazard Present
|
|
Limited Approach Boundary: 42 inches
|
|
Restricted Approach Boundary: 12 inches
|
|
Will the hands enter the RAB: No
|
|
Voltage Glove Class: 0
|
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
|
Incident Energy: 9.44 cal/cm2
|
|
Arc Flash Boundary: 56
|
|
Working Distance: 24 inches
|
|
Arc Flash PPE Level: 2+
|
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
|
Capacitor Bus Voltage:
|
|
Capacitor total stored energy (joules):
|
|
Discharge wait time (minutes):
|
Emergency Response Plan
|
Nearest Landline Location: adjacent room
|
|
Emergency Number to Call: 911
|
|
Sufficient cell phone signal? Yes
|
|
Clear exit path? Yes
|
|
AED Location: in lead's van
|
|
Fire Extinguisher Location: in adjacent room
|
|
Contact release method available and tested: Upstream breaker or switch
|
Environmental Conditions
|
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
|
Task Demands:
|
|
Work Environment:
|
|
Individual Capabilities:
|
|
Human Nature:
|
|
Error Precursor Mitigations:
reviewed error precursors with my second and discussed hazards. we determined we could proceed without extra mitigations. |
PPE Inspections
|
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles |
Notes / Other
|
no voltage exposure, mode 0, restoring power so vendor can test door function, donning level 4 PPE
|
Perform Job Breifing
|
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |