Time / Date: 5/23/2024 9:27:27
|
JSP ID: 2607
|
Scope of Work: Preventive maintenance
|
|
Work Order: W0373967
|
Building: 50A
|
Person in Charge: Justin solis
|
Lead / Supervisor: Delgado, Alex
|
Logged Email: juanjuarez37@lbl.gov
|
Division: Facilities
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Safety Watch
|
|
Second Person Identified: Juan juarez
|
|
List Other Participants:
|
|
Affected Persons Notified: Yes
|
Switching: Hazardous Switching
|
Panel / Equipment ID: 35C10A/50BAHU013
|
System Information Review: Panel Schedules
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
After the safety briefing we will established LOTO AND ZVV ,removed the access panel to perform visual inspection , thigh in screws and check electrical components, replaced air filters , checked indoor blower components, replaced belt ,reconnected power supply and performed a system test. |
Control of Work Area
Minimum Approach Boundary: 99”
|
Barricade Tape / Attendant: Attendant
|
Shock Risk Assessment
System Voltage: 120/208 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 25.9 cal/cm2
|
Arc Flash Boundary: 99”
|
Working Distance: 18 inches
|
Arc Flash PPE Level: 4
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage:
|
Capacitor total stored energy (joules):
|
Discharge wait time (minutes):
|
Emergency Response Plan
Nearest Landline Location: Outside room
|
Emergency Number to Call: 7911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: Front of elevator
|
Fire Extinguisher Location: Inside room
|
Contact release method available and tested: Voltage gloves
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
Insufficient lighting |
Error Precursors
Task Demands: Simultaneous or multiple tasks
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
At step at a time |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |