Time / Date: 5/30/2024 10:44:54
|
JSP ID: 2632
|
Scope of Work: Perform scheduled maintenance.
|
|
Work Order: Go over job scope. Gather information and perform shock hazard and arc flash hazard assessment. And establish correct ppe. Contact user. Conduct a safety briefing. Perform switching. Apply loto and verify zvv. Perform maintenance tasks. Remove loto and restore power. Check operations and return equipment back to service.
|
Building: 50 B
|
Person in Charge: Justin walker
|
Lead / Supervisor: Delgado, Alex
|
Logged Email: jwwalker@lbl.gov
|
Division: Facilities
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Larry antles
|
|
List Other Participants:
|
|
Affected Persons Notified: Yes
|
Switching: Hazardous Switching
|
Panel / Equipment ID: 480A5A-3. / 50B ac 012
|
System Information Review: Panel Schedules, Arc Flash Labels
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
|
Control of Work Area
Minimum Approach Boundary: 46 inches
|
Barricade Tape / Attendant: Attendant
|
Shock Risk Assessment
System Voltage: 277/480 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 5.42 cal/ cm2 cal/cm2
|
Arc Flash Boundary: 46 inches
|
Working Distance: 18 inches
|
Arc Flash PPE Level: 2
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage: Na
|
Capacitor total stored energy (joules): Na
|
Discharge wait time (minutes): Na
|
Emergency Response Plan
Nearest Landline Location: 50b room 1275
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: 50b Hal 2nd floor hall right of elevator
|
Fire Extinguisher Location: 50b room 1275
|
Contact release method available and tested: Upstream breaker or switch, Voltage gloves
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
Lookalike equipment |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
No current error precursors |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |