Time / Date: 6/28/2024 9:38:11
|
JSP ID: 2707
|
|
Scope of Work: Open bottom of MCC to take pictures of underground conduits.
|
|
|
Work Order: 382896
|
Building: 6
|
|
Person in Charge: Robert Ralph
|
Lead / Supervisor: Combs, Everett
|
|
Logged Email: RobertRalph@lbl.gov
|
Division: ALS
|
|
QEW Level: QEW 2
|
|
|
Modes of Work: Mode 2 - Energized Diagnostics, Testing and Troubleshooting, Visual Inspection
|
|
|
Second Person Requirement: Safety Watch
|
|
|
Second Person Identified: Chris Nelson
|
|
|
List Other Participants:
|
|
|
Affected Persons Notified: N/A
|
|
|
Switching: No Switching Required
|
Panel / Equipment ID: M304A3A
|
|
System Information Review: Arc Flash Labels
|
|
|
Control of Hazardous Energy: LOTO Not Required (Mode 2 or 3 only)
|
|
|
Equipment Condition: Properly installed, Properly maintained
|
|
Sequence of Job Steps
|
List basic sequence of steps from start to finish.
1. Job briefing 2. Barricade with Danger3.Put on appropriate PPE 4.Open MCC 5.Take photos 6.close MCC 7.remove barricades. |
Control of Work Area
|
Minimum Approach Boundary: 42
|
|
Barricade Tape / Attendant: Danger - Red
|
Shock Risk Assessment
|
System Voltage: 277/480 V ac
|
|
Limited Approach Boundary: 42 inches
|
|
Restricted Approach Boundary: 12 inches
|
|
Will the hands enter the RAB: No
|
|
Voltage Glove Class: 0
|
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
|
Incident Energy: 11 cal/cm2
|
|
Arc Flash Boundary: 69”
|
|
Working Distance: 18 inches
|
|
Arc Flash PPE Level: 4
|
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
|
Capacitor Bus Voltage:
|
|
Capacitor total stored energy (joules):
|
|
Discharge wait time (minutes):
|
Emergency Response Plan
|
Nearest Landline Location: Lobby B6
|
|
Emergency Number to Call: 911
|
|
Sufficient cell phone signal? Yes
|
|
Clear exit path? Yes
|
|
AED Location: Lobby B6
|
|
Fire Extinguisher Location: By column 5
|
|
Contact release method available and tested: Voltage gloves
|
Environmental Conditions
|
Does the environment present additional hazards that should be addressed?
Heavy traffic |
Error Precursors
|
Task Demands:
|
|
Work Environment:
|
|
Individual Capabilities:
|
|
Human Nature:
|
|
Error Precursor Mitigations:
Make sure all precursors have been discussed. |
PPE Inspections
|
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools |
Notes / Other
|
|
Perform Job Breifing
|
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |