QEW 1 / 2 / 3 Job Safety Plan

Electrical Safety
Back to Index
Time / Date: 7/12/2024 13:13:13
JSP ID: 2752
Scope of Work: Replace convenience wall power receptacle.

General Information

Work Order
388997
Building
55
Person in Charge
Alejandro Lopez
Lead / Supervisor
Ramer, Robert
Logged Email
Alopez2@lbl.gov
Division
Facilities

Work Planning

Modes of Work
☑ Mode 1 - LOTO & Zero Voltage Verification
QEW Level
QEW 2
Second Person Requirement
Not Required
Second Person Identified
n/a
Other Participants
n/a
Affected Persons Notified
N/A

System / Equipment

Switching
Non-Hazardous Switching
Panel / Equipment ID
29A15A1A
System Information Review
☑ Panel Schedules
Control of Hazardous Energy
Simple LOTO
Equipment Condition
☑ Properly installed
☑ All doors and covers closed and fully latched
☑ No signs of impending failure

Sequence of Job Steps

List basic sequence of steps from start to finish
LOTO circuit 29A15A1A-23, ZVV and replace wall power receptacle, remove LOTO and test power receptacle.

Control of Work Area

Minimum Approach Boundary
42 inches
Barricade Tape / Attendant
Danger - Red

Shock Risk Assessment

System Voltage
120 Vac
Limited Approach Boundary
42 inches
Restricted Approach Boundary
3 inches
Will the hands enter the RAB
No
Voltage Glove Class
00
Will any other part of the body enter the RAB
No

Arc Flash Risk Assessment

Incident Energy
4.23 cal/cm2
Arc Flash Boundary
40 inches
Working Distance
18 inches
Arc Flash PPE Level
Minimum PPE for Electrical Work
Incident Energy Reduction Measures
00

Capacitor Hazards

Capacitor Bus Voltage
n/a
Capacitor Total Stored Energy (Joules)
n/a
Discharge Wait Time (Minutes)
n/a

Emergency Response Plan

Nearest Landline Location
main corridor
Emergency Number to Call
911
Sufficient Cell Phone Signal
Yes
Clear Exit Path
Yes
AED Location
main corridor
Fire Extinguisher Location
main corridor
Contact Release Method Available and Tested
Voltage gloves

Environmental Conditions

Does the environment present additional hazards that should be addressed?
None

Error Precursors

Task Demands
Work Environment
Individual Capabilities
Human Nature
Error Precursor Mitigations
none

PPE Inspections

☑ Safety glasses (ANSI Z87)
☑ Arc-rated clothing (flash suit
☑ daily wear) including face shield
☑ balaclava
☑ hood.
☑ Hearing protection
☑ Rubber insulating gloves and leather protectors
☑ Non-melting footwear that fully covers the feet
☑ Removal of conductive articles
☑ Multimeter and other electrical test instruments

Notes / Other

none

Perform Job Briefing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan