Time / Date: 7/28/2024 10:06:00
|
JSP ID: 2781
|
Scope of Work: Repair UPS 2 UPM
|
|
Work Order: NA
|
Building: B59
|
Person in Charge: Ernie Jew
|
Lead / Supervisor: Grounds, Jeff
|
Logged Email: ejew@lbl.gov
|
Division: Comp Sci
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Eugene Acasio
|
|
List Other Participants: Eric Lucas
|
|
Affected Persons Notified: Yes
|
Switching: Hazardous Switching
|
Panel / Equipment ID: UPS 1 & 2
|
System Information Review: Single Line Drawing
|
|
Control of Hazardous Energy: Complex LOTO w/ RI
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
Notify Control room, Put UPS in bypass, Power down UPS, LOTO isolations, Perform ZVV, Perform work, Release LOTO, Power up UPS, Take UPS out of Bypass, Notify Control Room. |
Control of Work Area
Minimum Approach Boundary: 42"
|
Barricade Tape / Attendant: Warning - Orange
|
Shock Risk Assessment
System Voltage: 277/480 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 5.4 Cal/Cm2 cal/cm2
|
Arc Flash Boundary: 38"
|
Working Distance: 18 inches
|
Arc Flash PPE Level: 2
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage: NA
|
Capacitor total stored energy (joules): NA
|
Discharge wait time (minutes): NA
|
Emergency Response Plan
Nearest Landline Location: Container office
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: In Container Office
|
Fire Extinguisher Location: In UPS room
|
Contact release method available and tested: Rescue hook
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
Task Demands: Critical steps or irreversible acts
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
Follow CLP 383 LOTO procedures |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments, Longer multimeter leads |
Notes / Other
NA
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |