Logo

QEW 1 / 2 / 3 Job Safety Plan

Electrical Safety
Back to Index
Time / Date: 8/28/2024 9:08:00
JSP ID: 2884
Scope of Work: Open Gyrotron cabinet and remove Magnet power Supply for inspection and repair.

General Information

Work Order
N\A
Building
88
Person in Charge
Brendan Ford
Lead / Supervisor
Other
Logged Email
bpford@lbl.gov
Division
Other

Work Planning

Modes of Work
☑ Mode 0 - Electrically Safe Work Condition
☑ Mode 1 - LOTO & Zero Voltage Verification
QEW Level
QEW 2
Second Person Requirement
Standby Person
Second Person Identified
Nathaniel Bohm
Other Participants
Scott Small, John Garcia, Sean Zhong, Nathaniel Bohm
Affected Persons Notified
Yes

System / Equipment

Switching
Hazardous Switching
Panel / Equipment ID
CB 15 in panel 80A4A6A
System Information Review
☑ Single Line Drawing
☑ Panel Schedules
☑ Arc Flash Labels
Control of Hazardous Energy
Simple LOTO
Equipment Condition
☑ Properly installed
☑ Properly maintained
☑ All doors and covers closed and fully latched
☑ Not energizing equipment for the first time
☑ or after electrical repair

Sequence of Job Steps

List basic sequence of steps from start to finish
1:Make sure Gyrotron owner/users is notified and shutdown Gyrotron. 2:Switch CB 15 in panel 80A4A6A, 480 VAC with Arc Flash Hazard of 5.30 cal. 3:Apply Loto lock and tag on CB 15 and verify absence of voltage on TB 2 inside rear north side of Gyrotron enclosure. 4:Cover High Voltage Power Supply output leads just below Magnet power Supply and small access hole just to the right with rubber insulating blankets for the duration of the work. 5:Remove all connections to the Magnet power Supply and remove from enclosure. 6:Repair/replace Magnet power Supply. Remove rubber insulating blankets and close enclosure. 7:Remove Loto locks and switch CB 15 on and return control to Gyrotron owner/users after functional tests are complete.

Control of Work Area

Minimum Approach Boundary
42"
Barricade Tape / Attendant
Caution - Yellow

Shock Risk Assessment

System Voltage
277/480 V ac
Limited Approach Boundary
42 inches
Restricted Approach Boundary
12 inches
Will the hands enter the RAB
Yes
Voltage Glove Class
0
Will any other part of the body enter the RAB
No

Arc Flash Risk Assessment

Incident Energy
5.3 cal/cm2
Arc Flash Boundary
41"
Working Distance
18 inches
Arc Flash PPE Level
2
Incident Energy Reduction Measures
0

Capacitor Hazards

Capacitor Bus Voltage
Capacitor Total Stored Energy (Joules)
Discharge Wait Time (Minutes)

Emergency Response Plan

Nearest Landline Location
Less then 15' away just east of panel.
Emergency Number to Call
911
Sufficient Cell Phone Signal
Yes
Clear Exit Path
No
AED Location
E.M. shop and also inside front main entrance of the building.
Fire Extinguisher Location
45' to the South East, on walkway above stairs.
Contact Release Method Available and Tested
Rescue hook, Voltage gloves

Environmental Conditions

Does the environment present additional hazards that should be addressed?
None

Error Precursors

Task Demands
Work Environment
Individual Capabilities
Human Nature
Error Precursor Mitigations
Slow down and perform the work in a thoughtful manner.

PPE Inspections

☑ Safety glasses (ANSI Z87)
☑ Arc-rated clothing (flash suit
☑ daily wear) including face shield
☑ balaclava
☑ hood.
☑ Hearing protection
☑ Rubber insulating gloves and leather protectors
☑ Non-melting footwear that fully covers the feet
☑ Removal of conductive articles
☑ Multimeter and other electrical test instruments

Notes / Other

Perform Job Briefing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan