Time / Date: 9/4/2024 18:09:19
JSP ID: 2899
Scope of Work: ZVV eConntect box for Group LOTO overlocking crafts admin lock
Work Order: LP5410
Building: B72 rm
Person in Charge: Keola Baclayon
Lead / Supervisor: Other
Logged Email: kbaclayon@lbl.gov
Division: Other
QEW Level: QEW 2
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
Second Person Requirement: Standby Person
Second Person Identified: Ohmar Sowle
List Other Participants: Thermal Fisher
Affected Persons Notified: Yes
Switching: Non-Hazardous Switching
Panel / Equipment ID: 39A5A / PNL-022-72
System Information Review: Single Line Drawing, Panel Schedules, Arc Flash Labels, Panel does not exist in Single line. JIRA request added.
Control of Hazardous Energy: Complex LOTO (requires LP, CLP, FLP)
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair

Sequence of Job Steps

List basic sequence of steps from start to finish.

Lock on to craft admin lock, ZVV in

Control of Work Area

Minimum Approach Boundary: 42
Barricade Tape / Attendant: Danger - Red

Shock Risk Assessment

System Voltage: 120/208 V ac
Limited Approach Boundary: 42 inches
Restricted Approach Boundary: 12 inches
Will the hands enter the RAB: Yes
Voltage Glove Class: 0
Will any other part of the body enter the RAB: No

Arc Flash Risk Assessment

Incident Energy: 6.9 cal/cm2
Arc Flash Boundary: Na Class1.2b
Working Distance: No Arc Flash Hazard Present
Arc Flash PPE Level: 2
Incident Energy Reduction Measures: 0

Capacitor Hazards

Capacitor Bus Voltage: NA
Capacitor total stored energy (joules): NA
Discharge wait time (minutes): NA

Emergency Response Plan

Nearest Landline Location: B72 rm 110
Emergency Number to Call: 911
Sufficient cell phone signal? Yes
Clear exit path? Yes
AED Location: Portable from EHS
Fire Extinguisher Location: outside rm 102
Contact release method available and tested: Voltage gloves

Environmental Conditions

Does the environment present additional hazards that should be addressed?

None

Error Precursors

Task Demands:
Work Environment:
Individual Capabilities:
Human Nature:
Error Precursor Mitigations:

Hard copy available upon request.

PPE Inspections

Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit,
daily wear) including face shield,
balaclava,
hood.,
Hearing protection,
Rubber insulating gloves and leather protectors,
Non-melting footwear that fully covers the feet,
Removal of conductive articles,
Insulated tools,
Multimeter and other electrical test instruments

Notes / Other

Perform Job Breifing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan


Rev 2023.08.22.1