Time / Date: 9/13/2024 6:44:18
|
JSP ID: 2932
|
Scope of Work: Swap out heat detector in shed 79L.
|
|
Work Order: 393812
|
Building: B77 sheds
|
Person in Charge: Travis Ray and Ed Bekheet
|
Lead / Supervisor: Baird, Shawn
|
Logged Email: edbekheet@lbl.gov
|
Division: Facilities
|
QEW Level: QEW 1
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Travis Ray
|
|
List Other Participants:
|
|
Affected Persons Notified: Yes
|
Switching: Non-Hazardous Switching
|
Panel / Equipment ID: 79A-PNL-002. E732A
|
System Information Review: Single Line Drawing, Panel Schedules, Arc Flash Labels
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition:
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
1. Perform LOTO of main circuit feeding all sheds 2. Perform ZVV 3. Swap out heat detector once ZVV is complete and zero voltage is verified 4. Release LOTO 5. Test heat detector |
Control of Work Area
Minimum Approach Boundary: 42 in
|
Barricade Tape / Attendant: Attendant
|
Shock Risk Assessment
System Voltage: 120 Vac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 3 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 2.36 cal/cm2
|
Arc Flash Boundary: 26 in
|
Working Distance: No Arc Flash Hazard Present
|
Arc Flash PPE Level: Minimum PPE for Electrical Work
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage:
|
Capacitor total stored energy (joules):
|
Discharge wait time (minutes):
|
Emergency Response Plan
Nearest Landline Location: Rm 156B
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: By Rm 142 in Area 123 by stairwell
|
Fire Extinguisher Location: On 79A exterior wall by 77L shed
|
Contact release method available and tested: Voltage gloves
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
Confined space |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
Will be cautious and aware |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |