Time / Date: 11/8/2024 14:32:19
|
JSP ID: 3094
|
Scope of Work: Installing Cell Watch Battery Monitoring System and UPM replacement
|
|
Work Order: NA
|
Building: 59
|
Person in Charge: Ernie Jew
|
Lead / Supervisor: Grounds, Jeff
|
Logged Email: ejew@lbl.gov
|
Division: Comp Sci
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Eric Lucas
|
|
List Other Participants: Eugene Ocasio
Chap Elvina
|
|
Affected Persons Notified: Yes
|
Switching: Hazardous Switching
|
Panel / Equipment ID: UPS 1&2
|
System Information Review: Single Line Drawing, Panel Schedules, Arc Flash Labels
|
|
Control of Hazardous Energy: Complex LOTO (requires LP, CLP, FLP)
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
Notify Control Room Begin LOTO steps to put UPS in bypass/maintenance mode Perform Switching at UPS distribution board Power off UPS Open Input breakers to UPS Open all battery breakers Hang locks and tags at all isolation points and place keys in lock box Hang RI lock and tag on lock box Perform LOTO briefing with everyone joining LOTO Have all workers join LOTO Begin work |
Control of Work Area
Minimum Approach Boundary: 42
|
Barricade Tape / Attendant: Warning - Orange
|
Shock Risk Assessment
System Voltage: 277/480 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 5.4 cal/cm2
|
Arc Flash Boundary: 38"
|
Working Distance: 18 inches
|
Arc Flash PPE Level: 2
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage: NA
|
Capacitor total stored energy (joules): NA
|
Discharge wait time (minutes): NA
|
Emergency Response Plan
Nearest Landline Location: Container office
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: Container Office
|
Fire Extinguisher Location: In UPS room, near exit door
|
Contact release method available and tested: Rescue hook
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
NA |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
NA
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |