Time / Date: 3/6/2025 14:50:05
|
JSP ID: 3479
|
Scope of Work: remove broken prong from receptacle
|
|
Work Order: W0415062
|
Building: 53
|
Person in Charge: greg neidiger
|
Lead / Supervisor: Combs, Everett
|
Logged Email: gcn@lbl.gov
|
Division: ALS
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Not Required
|
|
Second Person Identified:
|
|
List Other Participants:
|
|
Affected Persons Notified: N/A
|
Switching: Non-Hazardous Switching
|
Panel / Equipment ID: 15A15A58A-11
|
System Information Review: Panel Schedules, Arc Flash Labels
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
1) LOTO/ZVV 2) remove prong 3) release LOTO and energize |
Control of Work Area
Minimum Approach Boundary:
|
Barricade Tape / Attendant:
|
Shock Risk Assessment
System Voltage: 120 Vac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 3 inches
|
Will the hands enter the RAB: No
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 1.71 cal/cm2
|
Arc Flash Boundary: 22in
|
Working Distance: No Arc Flash Hazard Present
|
Arc Flash PPE Level: Minimum PPE for Electrical Work
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage:
|
Capacitor total stored energy (joules):
|
Discharge wait time (minutes):
|
Emergency Response Plan
Nearest Landline Location: room adjacent to panel
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: in shop
|
Fire Extinguisher Location: in shop
|
Contact release method available and tested:
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
Heavy traffic |
Error Precursors
Task Demands:
|
Work Environment: Confusing displays or controls
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
Panel has two different panel designations. Will use rubber gloves when performing ZVV because of exposed prong protruding from "hot" side of receptacle. Extra caution will be taken to ensure receptacle is de-energized because of differing labels. |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |