QEW 1 / 2 / 3 Job Safety Plan

Electrical Safety
Back to Index
Time / Date: 3/28/2025 7:56:30
JSP ID: 3549
Scope of Work: Demo GP 1&4 pumps and all electrical equipment associated with it wires pipes motors etc,etc,.

General Information

Work Order
430635
Building
91 u
Person in Charge
A Turner
Lead / Supervisor
Hendrick, Jeffery
Logged Email
AJTurner2@lbl.gov
Division
Facilities

Work Planning

Modes of Work
☑ Mode 1 - LOTO & Zero Voltage Verification
QEW Level
QEW 3
Second Person Requirement
Standby Person
Second Person Identified
Avery Turner
Other Participants
None
Affected Persons Notified
Yes

System / Equipment

Switching
Non-Hazardous Switching
Panel / Equipment ID
E671A11A1A cuts 4&6
System Information Review
☑ Single Line Drawing
☑ Panel Schedules
☑ Arc Flash Labels
Control of Hazardous Energy
Complex LOTO (requires LP, CLP, FLP)
Equipment Condition
☑ All doors and covers closed and fully latched
☑ No signs of impending failure
☑ Not energizing equipment for the first time
☑ or after electrical repair

Sequence of Job Steps

List basic sequence of steps from start to finish
De Energize circuit establish LOTTO ZVV hang yellow tag on the lock Box.

Control of Work Area

Minimum Approach Boundary
18 inches
Barricade Tape / Attendant
Attendant

Shock Risk Assessment

System Voltage
277/480 V ac
Limited Approach Boundary
18
Restricted Approach Boundary
3 feet, 6 inches
Will the hands enter the RAB
No
Voltage Glove Class
0
Will any other part of the body enter the RAB
No

Arc Flash Risk Assessment

Incident Energy
1.35 cal/cm2
Arc Flash Boundary
19 inches
Working Distance
18 inches
Arc Flash PPE Level
1
Incident Energy Reduction Measures
0

Capacitor Hazards

Capacitor Bus Voltage
None
Capacitor Total Stored Energy (Joules)
None
Discharge Wait Time (Minutes)
0

Emergency Response Plan

Nearest Landline Location
Cell phone
Emergency Number to Call
911
Sufficient Cell Phone Signal
Yes
Clear Exit Path
Yes
AED Location
Fire Extinguisher Location
On site
Contact Release Method Available and Tested
Voltage gloves

Environmental Conditions

Does the environment present additional hazards that should be addressed?
None

Error Precursors

Task Demands
Work Environment
Individual Capabilities
Human Nature
Error Precursor Mitigations
None

PPE Inspections

☑ Safety glasses (ANSI Z87)
☑ Arc-rated clothing (flash suit
☑ daily wear) including face shield
☑ balaclava
☑ hood.
☑ Hearing protection
☑ Rubber insulating gloves and leather protectors
☑ Non-melting footwear that fully covers the feet
☑ Removal of conductive articles
☑ Insulated tools
☑ Multimeter and other electrical test instruments

Notes / Other

None

Perform Job Briefing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan