					Time / Date: 4/18/2025 10:50:08				 				
				 | 
				
				 
					JSP ID: 3647				 
				 | 
				
| 
				 
					Scope of Work: Disconnect wiring between heater ring and Heater control boxes.  Unmount boxes and return them to LBL				 				
				 | 
				|
| 
				 
					Work Order: 				 				
				 | 
				
				 
					Building: Pt Reyes Field Site				 				
				 | 							
				
| 
				 
					Person in Charge: Todd Wood				 				
				 | 
				
				 
					Lead / Supervisor: Other				 
				 | 
				
| 
				 
					Logged Email: TJWood@lbl.gov				 				
				 | 
				
				 
					Division: Other				 				
				 | 
				
| 
				 
					QEW Level: QEW 1				 				
				 | 
				
				 | 
				
| 
				 
					Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification				 				
				 | 
				|
| 
				 
					Second Person Requirement: Not Required				 				
				 | 
				|
| 
				 
					Second Person Identified: 				 				
				 | 
				|
| 
				 
					List Other Participants: 				 				
				 | 
				|
| 
				 
					Affected Persons Notified: Yes				 				
				 | 
				|
| 
				 
					Switching: No Switching Required				 				
				 | 
				
				 
					Panel / Equipment ID: PP1-8				 
				 | 
				
| 
				 
					System Information Review: 				 				
				 | 
				|
| 
				 
					Control of Hazardous Energy: Cord & Plug LOTO				 				
				 | 
				|
| 
				 
					Equipment Condition: 				 				
				 | 
				|
Sequence of Job Steps
| 
				 
					List basic sequence of steps from start to finish. 				
				1. Establish Loto - Unplug 240 VAC plug, place a cord cap lock and tag. 2. Open enclosure - preform ZVV 3. ensure all breakers in the panel are OFF 4. disconnect phases and ground for the 2 heater circuits. 5. disconnect the low voltage signals from the datalogger 6. apply tape to protect all exposed wire ends 7. remove enclosures from the plywood backpanel  | 
				
Control of Work Area
| 
				 
					Minimum Approach Boundary: 42				 				
				 | 
				
| 
				 
					Barricade Tape / Attendant: 				 
				 | 
				
Shock Risk Assessment
| 
				 
					System Voltage: 120/240 V ac				 				
				 | 
				
| 
				 
					Limited Approach Boundary: 42 inches				 				
				 | 
				
| 
				 
					Restricted Approach Boundary: 12 inches				 				
				 | 
				
| 
				 
					Will the hands enter the RAB: Yes				 				
				 | 
				
| 
				 
					Voltage Glove Class: 0				 				
				 | 
				
| 
				 
					Will any other part of the body enter the RAB: No				 				
				 | 
				
Arc Flash Risk Assessment
| 
				 
					Incident Energy: NA cal/cm2
				 				
				 | 
				
| 
				 
					Arc Flash Boundary: NA				 				
				 | 
				
| 
				 
					Working Distance: No Arc Flash Hazard Present				 				
				 | 
				
| 
				 
					Arc Flash PPE Level: Minimum PPE for Electrical Work				 				
				 | 
				
| 
				 
					Incident Energy Reduction Measures: 0				 				
				 | 
				
Capacitor Hazards
| 
				 
					Capacitor Bus Voltage: NA				 				
				 | 
				
| 
				 
					Capacitor total stored energy (joules): NA				 				
				 | 
				
| 
				 
					Discharge wait time (minutes): NA				 				
				 | 
				
Emergency Response Plan
| 
				 
					Nearest Landline Location: Pt Reyes House				 				
				 | 
				
| 
				 
					Emergency Number to Call: 911				 				
				 | 
				
| 
				 
					Sufficient cell phone signal? Yes				 				
				 | 
				
| 
				 
					Clear exit path? Yes				 				
				 | 
				
| 
				 
					AED Location: 				 				
				 | 
				
| 
				 
					Fire Extinguisher Location: Barn				 				
				 | 
				
| 
				 
					Contact release method available and tested: Upstream breaker or switch				 				
				 | 
				
Environmental Conditions
| 
				 
					Does the environment present additional hazards that should be addressed? 				
				Wet location, Lookalike equipment  | 
				
Error Precursors
| 
				 
					Task Demands: 				 				
				 | 
				
| 
				 
					Work Environment: 				 				
				 | 
				
| 
				 
					Individual Capabilities: 				 				
				 | 
				
| 
				 
					Human Nature: 				 				
				 | 
				
| 
				 
					Error Precursor Mitigations:  				
				Consult task list, verbalize steps  | 
				
PPE Inspections
| 
				 
					Safety glasses (ANSI Z87), 				
				Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments  | 
				
Notes / Other
| 
				 | 
				
Perform Job Breifing
| 
				 
					PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.  				
				A Job Briefing at a minimum must include: 
 Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov  | 
				