Time / Date: 5/1/2025 16:21:56
|
JSP ID: 3696
|
Scope of Work: Bench top testing of experimental DC-DC power supply
|
|
Work Order:
|
Building: 90
|
Person in Charge: Ari Harding
|
Lead / Supervisor: Other
|
Logged Email: aharding@lbl.gov
|
Division: Other
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 2 - Energized Diagnostics, Testing and Troubleshooting, Visual Inspection
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Carla Pinzon
|
|
List Other Participants: None
|
|
Affected Persons Notified: N/A
|
Switching: No Switching Required
|
Panel / Equipment ID: N/A
|
System Information Review: N/A
|
|
Control of Hazardous Energy: Cord & Plug LOTO
|
|
Equipment Condition:
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
1. Connect CHROMA DC POWER SUPPLY, connect Chroma DC load 2. Cover with insulated sheeting for testing 3. Turn on power supply and load 4. Start testing at 50 vdc, 3 amps limit and troubleshoot as needed. 5. Ramp up voltage to 250 in steps of 50 volts if initial function test is successful. |
Control of Work Area
Minimum Approach Boundary: 42 inches
|
Barricade Tape / Attendant: Danger - Red
|
Shock Risk Assessment
System Voltage: 250 vdc
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: Yes
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: Minimal cal/cm2
|
Arc Flash Boundary: N/A
|
Working Distance: No Arc Flash Hazard Present
|
Arc Flash PPE Level: Minimum PPE for Electrical Work
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage: Not significant
|
Capacitor total stored energy (joules): N/A
|
Discharge wait time (minutes): N/A
|
Emergency Response Plan
Nearest Landline Location: Office next foor
|
Emergency Number to Call: 911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: Lobby of B90
|
Fire Extinguisher Location: Hallway
|
Contact release method available and tested: Not needed
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities: Unfamiliar with, or first time performing task
|
Human Nature:
|
Error Precursor Mitigations:
Proof of concept testing, take time and perform debugging at safe voltage levels |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |