JSP ID: 3742
|
Scope of Work: Loto, ZVV, investigate existing branch circuit wiring and install new raceways and jboxes for cubicle rearrangement. Pull in new conductors, inspect.
|
|
Work Order: 404719
|
Building: 69
|
Person in Charge: Shane Miller
|
Lead / Supervisor: Secheck, Stephen
|
Logged Email: spmiller@lbl.gov
|
Division: Facilities
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Standby Person
|
|
Second Person Identified: Alex Lopez
|
|
List Other Participants: Steve Sechak
|
|
Affected Persons Notified: Yes
|
Switching: Non-Hazardous Switching
|
Panel / Equipment ID: 217A1A3A
|
System Information Review: Panel Schedules, Arc Flash Labels
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition: Properly installed, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
1. Dawn the proper PPE 2. Apply Loto at panel 217A1A3A ckt 4 3. Hang red locks 4. ZVV at panel 233A 5. Investigate existing branch circuits 6. Install new raceways/jboxes 7. Pull in new branch circuit wiring 8. Add new breakers to panel 233A and tie in new branch circuit wires. 9. Inspect rough in and megger wire 10. Leave all new wiring in electrical safe condition. Hang blue admin. Locks on newly installed breakers. 11. Release LOTO at panel 217A1A3A 12. Clean up and wait for new cubicles to be installed. |
Control of Work Area
Minimum Approach Boundary: 42”
|
Barricade Tape / Attendant: Attendant
|
Shock Risk Assessment
System Voltage: 277/480 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: No
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 4.09cal/cm2 cal/cm2
|
Arc Flash Boundary: 35”
|
Working Distance: 18 inches
|
Arc Flash PPE Level: 2
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage:
|
Capacitor total stored energy (joules):
|
Discharge wait time (minutes):
|
Emergency Response Plan
Nearest Landline Location: Using cell phone with good signal
|
Emergency Number to Call: X6999
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: In Vehicle outside building, 100’ away
|
Fire Extinguisher Location: In break room 35’ away
|
Contact release method available and tested: Voltage gloves
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
None |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments |
Notes / Other
None
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include: