Time / Date: 12/21/2022 7:48:17
JSP ID: 379
Scope of Work: Release LOTO LP4712 Re Energize Water Jet For Contractor Support for Voltage Testing and re establish the LOTO When Testing is Done.
Work Order: 299210
Building:
Person in Charge: Christopher Nelson
Lead / Supervisor: Secheck, Stephen
Logged Email: cnelson@lbl.gov
Division: Facilities
QEW Level: QEW 2
Modes of Work: Mode 1 - LOTO & Zero Voltage Verification, Mode 2 - Energized Diagnostics, Testing and Troubleshooting, Visual Inspection
Second Person Requirement: Standby Person
Second Person Identified: Alex Lopez
List Other Participants: Alex Harrouz Cal Neva Contractor
Affected Persons Notified: Yes
Switching: Non-Hazardous Switching
Panel / Equipment ID: 72C2A
System Information Review: Arc Flash Labels, LOTO permit 4712 and contractors MOP
Control of Hazardous Energy: Complex LOTO w/ RI
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair

Sequence of Job Steps

List basic sequence of steps from start to finish.

Release LOTO Switch On Test Switch off and Establish LOTO hang HEC lock

Control of Work Area

Minimum Approach Boundary: 42 inches
Barricade Tape / Attendant: Danger - Red

Shock Risk Assessment

System Voltage: 277/480 V ac
Limited Approach Boundary: 42 inches
Restricted Approach Boundary: 12 inches
Will the hands enter the RAB: Yes
Voltage Glove Class: 0
Will any other part of the body enter the RAB: No

Arc Flash Risk Assessment

Incident Energy: <0.55 cal^cm2 cal/cm2
Arc Flash Boundary: 18 inches
Working Distance: 18 inches
Arc Flash PPE Level: 2
Incident Energy Reduction Measures: 0

Capacitor Hazards

Capacitor Bus Voltage: NA
Capacitor total stored energy (joules): NA
Discharge wait time (minutes): NA

Emergency Response Plan

Nearest Landline Location: Room 105 A
Emergency Number to Call: 911
Sufficient cell phone signal? Yes
Clear exit path? Yes
AED Location: At the main entrance of the building
Fire Extinguisher Location: Inside the room 105
Contact release method available and tested: Voltage gloves

Environmental Conditions

Does the environment present additional hazards that should be addressed?

None

Error Precursors

Task Demands: Repetitive actions or monotony
Work Environment: Distractions/interruptions
Individual Capabilities:
Human Nature:
Error Precursor Mitigations:

Don’t get Distracted stay focused on the task

PPE Inspections

Notes / Other

Perform Job Breifing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan


Rev 2023.08.22.1
Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov