					Time / Date: 10/24/2025 12:28:39				 | 
					JSP ID: 4239				 | 
| 
					Scope of Work: Replace bad gfi device on roof of 70A				 | |
| 
					Work Order: 465216				 | 
					Building: 70A				 | 
| 
					Person in Charge: Shane Miller				 | 
					Lead / Supervisor: Secheck, Stephen				 | 
| 
					Logged Email: spmiller@lbl.gov				 | 
					Division: Facilities				 | 
| 
					QEW Level: QEW 2				 |  | 
| 
					Modes of Work: Mode 1 - LOTO & Zero Voltage Verification				 | |
| 
					Second Person Requirement: Standby Person				 | |
| 
					Second Person Identified: Armando Uribe				 | |
| 
					List Other Participants: 				 | |
| 
					Affected Persons Notified: N/A				 | |
| 
					Switching: Non-Hazardous Switching				 | 
					Panel / Equipment ID: E31A18A2A46A ckt 7				 | 
| 
					System Information Review: Panel Schedules, Arc Flash Labels				 | |
| 
					Control of Hazardous Energy: Simple LOTO				 | |
| 
					Equipment Condition: Properly installed, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair				 | |
Sequence of Job Steps
| 
					List basic sequence of steps from start to finish. Loto at panel E31A18A2A46A ckt 7 remove and replace gfci outlet release Loto and test outlet | 
Control of Work Area
| 
					Minimum Approach Boundary: 70"				 | 
| 
					Barricade Tape / Attendant: Attendant				 | 
Shock Risk Assessment
| 
					System Voltage: 120/208 V ac				 | 
| 
					Limited Approach Boundary: 42 inches				 | 
| 
					Restricted Approach Boundary: 12 inches				 | 
| 
					Will the hands enter the RAB: No				 | 
| 
					Voltage Glove Class: 0				 | 
| 
					Will any other part of the body enter the RAB: No				 | 
Arc Flash Risk Assessment
| 
					Incident Energy: 10.5 cal/cm2 cal/cm2
				 | 
| 
					Arc Flash Boundary: 70"				 | 
| 
					Working Distance: 18 inches				 | 
| 
					Arc Flash PPE Level: Minimum PPE for Electrical Work				 | 
| 
					Incident Energy Reduction Measures: 0				 | 
Capacitor Hazards
| 
					Capacitor Bus Voltage: 				 | 
| 
					Capacitor total stored energy (joules): 				 | 
| 
					Discharge wait time (minutes): 				 | 
Emergency Response Plan
| 
					Nearest Landline Location: Corridor 70A				 | 
| 
					Emergency Number to Call: x6999				 | 
| 
					Sufficient cell phone signal? Yes				 | 
| 
					Clear exit path? Yes				 | 
| 
					AED Location: Corridor 70A				 | 
| 
					Fire Extinguisher Location: Corridor 70A				 | 
| 
					Contact release method available and tested: Voltage gloves				 | 
Environmental Conditions
| 
					Does the environment present additional hazards that should be addressed? None | 
Error Precursors
| 
					Task Demands: 				 | 
| 
					Work Environment: 				 | 
| 
					Individual Capabilities: 				 | 
| 
					Human Nature: 				 | 
| 
					Error Precursor Mitigations:  none | 
PPE Inspections
| 
					Safety glasses (ANSI Z87), Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Hearing protection, Rubber insulating gloves and leather protectors, Non-melting footwear that fully covers the feet, Removal of conductive articles, Insulated tools, Multimeter and other electrical test instruments | 
Notes / Other
|  | 
Perform Job Breifing
| 
					PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.  A Job Briefing at a minimum must include: 
 Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov | 