Logo

QEW 1 / 2 / 3 Job Safety Plan

Electrical Safety
Back to Index
Time / Date: 1/30/2026 7:48:31
JSP ID: 4504
Scope of Work: Replace existing fixtures

General Information

Work Order
W0475280
Building
84
Person in Charge
Arnel Jugarap
Lead / Supervisor
Keusch, Justen
Logged Email
efhampton@lbl.gov
Division
Facilities

Work Planning

Modes of Work
☑ Mode 0 - Electrically Safe Work Condition
QEW Level
QEW 2
Second Person Requirement
Not Required
Second Person Identified
Egon Hampton
Other Participants
Sayee Chea
Affected Persons Notified
Yes

System / Equipment

Switching
Non-Hazardous Switching
Panel / Equipment ID
460A4A9A
System Information Review
☑ Arc Flash Labels
Control of Hazardous Energy
Simple LOTO
Equipment Condition
☑ Properly installed
☑ Properly maintained
☑ All doors and covers closed and fully latched
☑ No signs of impending failure
☑ Not energizing equipment for the first time
☑ or after electrical repair

Sequence of Job Steps

List basic sequence of steps from start to finish
Lotto / zvv/ remove fixture/replace fixture/energize/remove lottto

Control of Work Area

Minimum Approach Boundary
18”
Barricade Tape / Attendant
Attendant

Shock Risk Assessment

System Voltage
277/480 V ac
Limited Approach Boundary
42 inches
Restricted Approach Boundary
12 inches
Will the hands enter the RAB
No
Voltage Glove Class
0
Will any other part of the body enter the RAB
No

Arc Flash Risk Assessment

Incident Energy
3,17 cal/cm2
Arc Flash Boundary
31”
Working Distance
18 inches
Arc Flash PPE Level
2
Incident Energy Reduction Measures
0

Capacitor Hazards

Capacitor Bus Voltage
Na
Capacitor Total Stored Energy (Joules)
Na
Discharge Wait Time (Minutes)
Na

Emergency Response Plan

Nearest Landline Location
Main entrance
Emergency Number to Call
699
Sufficient Cell Phone Signal
Yes
Clear Exit Path
Yes
AED Location
Main entrance
Fire Extinguisher Location
3rd
Contact Release Method Available and Tested
Upstream breaker or switch, Voltage gloves

Environmental Conditions

Does the environment present additional hazards that should be addressed?
None

Error Precursors

Task Demands
Work Environment
Individual Capabilities
Human Nature
Error Precursor Mitigations
Scaffolding

PPE Inspections

☑ Safety glasses (ANSI Z87)
☑ Arc-rated clothing (flash suit
☑ daily wear) including face shield
☑ balaclava
☑ hood.
☑ Hearing protection
☑ Rubber insulating gloves and leather protectors
☑ Non-melting footwear that fully covers the feet
☑ Removal of conductive articles
☑ Insulated tools
☑ Multimeter and other electrical test instruments
☑ Ladder

Notes / Other

Na

Perform Job Briefing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan