Time / Date: 1/26/2023 11:22:44
JSP ID: 513
Scope of Work: Pm on 6 roof ac 001
Work Order: 299055
Building:
Person in Charge: Antonio collado
Lead / Supervisor: Delgado, Alex
Logged Email: Acollado@lbl.gov
Division: Facilities
QEW Level: QEW 2
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
Second Person Requirement: Standby Person
Second Person Identified: Alex Delgado
List Other Participants:
Affected Persons Notified: Yes
Switching: Non-Hazardous Switching
Panel / Equipment ID: 304a7a3a/ ac 001
System Information Review: Panel Schedules
Control of Hazardous Energy: Simple LOTO
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair

Sequence of Job Steps

List basic sequence of steps from start to finish.

Loto out zvv, pm place back on and check ops

Control of Work Area

Minimum Approach Boundary: 42
Barricade Tape / Attendant: Attendant

Shock Risk Assessment

System Voltage: 277/480 V ac
Limited Approach Boundary: 42 inches
Restricted Approach Boundary: 3 inches
Will the hands enter the RAB: Yes
Voltage Glove Class: 0
Will any other part of the body enter the RAB: No

Arc Flash Risk Assessment

Incident Energy: 0.08 cal/cm2
Arc Flash Boundary: 14 inches
Working Distance: No Arc Flash Hazard Present
Arc Flash PPE Level: 2
Incident Energy Reduction Measures: 0

Capacitor Hazards

Capacitor Bus Voltage:
Capacitor total stored energy (joules):
Discharge wait time (minutes):

Emergency Response Plan

Nearest Landline Location: Control room
Emergency Number to Call: 699
Sufficient cell phone signal? Yes
Clear exit path? Yes
AED Location: Control room
Fire Extinguisher Location: Near entrance to right
Contact release method available and tested: Voltage gloves

Environmental Conditions

Does the environment present additional hazards that should be addressed?

None

Error Precursors

Task Demands:
Work Environment:
Individual Capabilities:
Human Nature:
Error Precursor Mitigations:

Going up ladder

PPE Inspections

Notes / Other

Perform Job Breifing

PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.

A Job Briefing at a minimum must include:
  1. Detailed Scope of Work
  2. Shock and arc flash hazards for each task
  3. Controls to mitigate the hazards (procedures, precautions, energy source controls, PPE requirements)
  4. Work area controls (barricades, signs, attendants)
  5. Emergency Response Plan


Rev 2023.08.22.1
Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov