Time / Date: 3/14/2023 8:13:00
|
JSP ID: 745
|
Scope of Work: troubleshoot lost power to three standard receptacles.
|
|
Work Order: 314731
|
Building:
|
Person in Charge: Jared Tissot
|
Lead / Supervisor: Secheck, Stephen
|
Logged Email: jtissot@lbl.gov
|
Division: Facilities
|
QEW Level: QEW 2
|
|
Modes of Work: Mode 0 - Electrically Safe Work Condition, Mode 1 - LOTO & Zero Voltage Verification
|
|
Second Person Requirement: Not Required
|
|
Second Person Identified: NA
|
|
List Other Participants: NA
|
|
Affected Persons Notified: Yes
|
Switching: Non-Hazardous Switching
|
Panel / Equipment ID: 47A3A33A46A-19
|
System Information Review: Panel Schedules, Arc Flash Labels
|
|
Control of Hazardous Energy: Simple LOTO
|
|
Equipment Condition: Properly installed, Properly maintained, All doors and covers closed and fully latched, No signs of impending failure, Not energizing equipment for the first time, or after electrical repair
|
Sequence of Job Steps
List basic sequence of steps from start to finish.
preform voltage reading, switching loto and zvv. diagnose issue causing power loss. fix issue, restore power. test volatge |
Control of Work Area
Minimum Approach Boundary: 42 INCHES
|
Barricade Tape / Attendant:
|
Shock Risk Assessment
System Voltage: 120/208 V ac
|
Limited Approach Boundary: 42 inches
|
Restricted Approach Boundary: 12 inches
|
Will the hands enter the RAB: No
|
Voltage Glove Class: 0
|
Will any other part of the body enter the RAB: No
|
Arc Flash Risk Assessment
Incident Energy: 0.2 cal/cm2
|
Arc Flash Boundary: 6 INCHES
|
Working Distance: 18 inches
|
Arc Flash PPE Level: Minimum PPE for Electrical Work
|
Incident Energy Reduction Measures: 0
|
Capacitor Hazards
Capacitor Bus Voltage: NA
|
Capacitor total stored energy (joules): NA
|
Discharge wait time (minutes): Na
|
Emergency Response Plan
Nearest Landline Location: 74 229
|
Emergency Number to Call: 7911
|
Sufficient cell phone signal? Yes
|
Clear exit path? Yes
|
AED Location: B74 HALLWAY
|
Fire Extinguisher Location: 229
|
Contact release method available and tested:
|
Environmental Conditions
Does the environment present additional hazards that should be addressed?
None |
Error Precursors
Task Demands:
|
Work Environment:
|
Individual Capabilities:
|
Human Nature:
|
Error Precursor Mitigations:
NA |
PPE Inspections
Safety glasses (ANSI Z87),
Arc-rated clothing (flash suit, daily wear) including face shield, balaclava, hood., Multimeter and other electrical test instruments |
Notes / Other
|
Perform Job Breifing
PIC Conducts the Job Briefing. Cover all the contents of the Job Safety Plan.
A Job Briefing at a minimum must include:
Rev 2023.08.22.1 Form Content and Feedback Contact: Michael Rose -- mvr@lbl.gov |