List basic sequence of steps from start to finish
Notify Operations of power disruption for PDU repairs
Set up LOTO work zone with warning tape and signage
Perform LOTO briefing
Switch power off and hang lock and tag at 590A22A-1,3,5 for PDU-22
ZVV at PDU-22
Have Vertiv hang LOTO lock and tag at 590A22A-1,3,5
Perform work
Notify Operations of re-energization of PDU-22
Remove LOTO
Swithc power on at 590A22A-1,3,5
Verify display functions as intended
End of jog